About UI
  Company Profile
  News & Information
  Transmission Services
  UI Projects
  Trumbull
  Careers
  UI in the Community
  Doing Business With UI
 
 

Trumbull Substation

The Trumbull Substation Project is the first in a series of projects undertaken by UI to upgrade our ability to deliver safe and reliable electricity to our customers. During the past 10 years residential use of electricity in the Trumbull area has increased by 38%. Commercial use has increased by 45% during the same period. Customer demand for electricity in the Trumbull area is expected to continue to increase going forward.

At the present time, there is no substation in Trumbull. None had been required during the last system upgrade. All customers in the Town of Trumbull are supplied from two substations --- one located in Shelton and the other in Bridgeport. Without the addition of the new substation, the Trumbull area is at high risk of experiencing delivery problems during periods of peak demand. By building the new substation, Trumbull customers will have their electricity requirements addressed locally. It will also improve the ability of the Shelton and Bridgeport substations to continue effectively meeting their local areas electricity demands.

The construction schedule for the Trumbull project is:

Begin Construction
07/16/2007
Steel Structures Delivered
11/09/2007
Begin Concrete Wall Construction
10/01/2007
Circuit Breakers Installation Complete
11/02/2007
PDC Delivered
11/30/2007
Site Grading Completed
11/28/2007
Concrete Wall Completed
03/09/2008
Equipment Installation Complete
03/11/2008
Substation Energized
04/12/2008
Begin Landscaping
TBD
Landscaping Complete
TBD
Construction Complete
06/15/2008

 