RFP for Fuel Cell Procurement Under Public Act 21-162
The RFP for Fuel Cell Procurement Under Public Act 21-162 is now closed
RFP Schedule
Action Item |
Date |
Release of RFP |
November 3, 2021 |
Bid Forms Due |
November 18, 2021 by 1:00 p.m. (Eastern Prevailing Time “EPT”), at which time the Pricing shall become firm, irrevocable, and binding. |
Selection and Notification of Winning Bidders |
On or about December 3, 2021 |
Service Agreement Execution |
After Selection and Notification of Winning Bidders. Bidders will have to return partially executed Service Agreements by the date established by the Companies which is expected to be approximately 5 business days. |
Service Agreement(s) Filed with PURA |
On or about January 3, 2022 |
Commencement of Service |
In accordance with Service Agreements |
All Bid Submissions must be submitted via email to: UIPower@uinet.com before November 18, 2021 at 1 PM.
Please note, as of 11/4/2021 at 9:50 AM, the RFP Document and Bid Form Instructions linked below have been modified due to UI's submittal of a revised Order No. 2 – Fuel Cell Electricity Generation Project Bid Form, as directed by PURA.
Documents
Service Agreement and Terms and Conditions
UI Bid Certification Form (Required to Bid)
Supplemental Bid Information (Required to Bid)
Carbon Neutrality Form (Required to Bid)
Manufactured Technology Supplier Affidavit
Manufactured Technology Bidder Affidavit
Performance Assurance Instructions