Standard Service and Last Resort Service RFPs
2022 Standard Service and Last Resort Service
Wednesday January 19, 2022 - Bid Day
Item  | 
         Date  | 
        
RFP Issued  | 
         December 15, 2021  | 
        
Bidder Information Forms Due (Forms Available on UI Wholesale Power Procurement Website)  | 
         Monday, January 3, 2022: 4:00 PM  | 
        
New Bidder Comments on Master WPSA Due  | 
         Friday, January 7, 2022: 4:00 PM  | 
        
New Bidder Master WPSA Discussions/Negotiations  | 
         Friday, January 14, 2022 through Friday, January 21, 2022  | 
        
Last Questions/inquiries for Q&A  | 
         Thursday, January 13, 2022: 4:00 PM  | 
        
New Bidder Master WPSA Fully Executed  | 
         Thursday, January 13, 2022: 4:00 PM  | 
        
Bid Assurance Due  | 
         Thursday, January 13, 2022: 4:00 PM  | 
        
Final Binding Bids Due  | 
         Wednesday, January 19, 2022: 10:00 AM  | 
        
Expected Notification of Winning Bidder(s)  | 
         Wednesday, January 19, 2022: By 1:00 PM  | 
        
Executed Confirmations and Guarantees Due Via E-Mail or FAX  | 
         Thursday, January 20, 2022: Close of Business  | 
        
Original Guarantees Due  | 
         Monday, January 24, 2022: Close of Business  | 
        
Mapping of GST and LPT Load for Jan 2022 Bid Day
For the one-year period that ended November 30, 2021 the following mapping represents actual mapping of GST and LPT load: For GST, 72.7% was mapped to Standard Service eligibility for energy (kWh) and 71.8% for demand (kW). For LPT, 33.0% was mapped to Standard Service eligibility for energy and 32.6% for demand. For GST, 27.3% was mapped to Last Resort Service eligibility for energy (kWh) and 28.2% for demand (kW). For LPT, 67.0% was mapped to Last Resort Service eligibility for energy and 67.4% for demand.