Main Activities During Reporting Period

Continued preparation and review of the following Project-related documents/reports for submittal to CTDEEP:

  1. Revised English Station First Floor and Interstitial Fill Investigation Summary Report. Revisions based on Supplemental Investigations completed in December 2021 thru February 2022 and the Boiler 13 IRM Concrete Investigations completed in February 2023.
  2. Revised English Station Boiler 1-12 Environmental Media Investigation Summary Report.
  3. Revised English Station Western Side Environmental Media Investigation Summary Report.
  4. English Station – Boiler #13 Interim Remedial Measures PCB Remedial Action Report

Perform required inspections of:

  1. Erosion and sediment controls (re)approved under CT DEEP permit number GSN003422 on a monthly frequency.
  2. Eight Significant Environmental Hazard (SEH) areas on a bi-weekly frequency.
     

Future Activities

Submit the following reports to CTDEEP:

  1. English Station – Boiler #13 Interim Remedial Measures PCB Remedial Action Report.
  2. Revised English Station Boiler 1-12 Environmental Media Investigation Summary Report.
  3. Revised English Station Western Side Environmental Media Investigation Summary Report.
  4. Revised English Station First Floor and Interstitial Fill Investigation Summary Report. Revisions based on Supplemental Investigations completed in December 2021 thru February 2022 and the Boiler 13 IRM Concrete Investigations completed in February 2023.
  5. Revised Plans and Specifications for Phase 1 Soil Remediation.
     

Site Security

Enhancements were made to approximately 50 feet of the fence along Grand Avenue by adding a bottom rail and installing razor wire along the inside of the fence to further deter trespassers.

Meeting held on 3/21/2024 with UI and personnel from the City of New Haven Emergency Operations and Engineering departments to discuss site security, trespassing, NHPD response, security system, and exclusion zone fence.

Continue to maintain the security measures put in place by, and acquired from, the current property owners and as upgraded by UI.
 